Making a new building solar-ready can cost relatively little when the necessary provisions are included in the original design. Retrofitting conduits, mounting provisions, earthing and structural supports after construction is complete can be considerably more expensive. The actual cost difference depends on the building and the installation requirements.
The most expensive mistake is often not forgetting to install solar. It is designing the roof without considering where the water tanks, lift room, parapet and other services will sit. Poor placement can reduce the usable roof area, create avoidable shading and limit the solar capacity that can be installed later.
Why one small structure can ruin so much roof
Winter shading deserves particular attention when planning a rooftop solar installation.
At Indore's latitude of roughly 22.7°N, the midday sun is relatively low in the sky during December. A rooftop structure therefore casts a longer shadow than it would around noon in summer. The shadow becomes longer still in the morning and afternoon, when the sun is lower.
For example, a 3-metre-high structure can cast a shadow several metres long in winter. The exact length depends on the sun's elevation, the time of day and the obstruction's orientation. The shadow also moves throughout the day, so the affected area is not simply a fixed rectangle behind the structure.
A lift room, overhead tank or other obstruction may affect several rows of panels, maintenance access and the layout of electrical strings. The actual capacity lost depends on the roof geometry, panel layout, shading pattern and system design.
A preliminary planning estimate of around 95 square feet per kW may be useful for a flat RCC roof, but it is not a guaranteed space requirement. Walkways, setbacks, obstructions, panel orientation and maintenance access can change the capacity that fits.
Key takeaway: give your architect a solar-layout requirement before the roof plan is finalised. As a starting point, keep taller obstructions away from the areas intended for panels and ask the solar designer to assess winter shadows before fixing the locations of rooftop services.
Where each service should go
Planning rooftop services before construction is usually much easier than relocating them afterwards. For many buildings, placing taller obstructions towards the northern side of the roof can reduce shading on panels located to their south, but the final arrangement must be checked against the building orientation and actual shadow paths.
- Lift machine room and stair overrun. Consider locating these towards the northern side of the roof where the building design permits. Their height, structural requirements, access and fire-safety needs must be considered before finalising the position.
- Overhead water tanks. Group tanks where practical and coordinate their position with the solar layout. Several scattered tanks can create multiple shaded areas and make panel placement less efficient.
- Air-conditioning outdoor units. Consider wall-mounted or dedicated service areas where permitted by the equipment manufacturer and building design. Roof-mounted units can occupy useful space and interfere with access or panel layout.
- Vents, plumbing stacks and antenna masts. Coordinate their positions with the solar designer. Even relatively narrow objects can cause shading, and the effect depends on the panel and string configuration.
- Parapet walls. Consider the height and location of parapets when designing the array. A parapet that is too tall or too close to the panels can cast shadows, but minimum edge protection and applicable building-safety requirements must not be compromised.
The space needed for a rooftop array is explained in our breakdown of roof space needed for solar panels. The indicative area per kW varies by roof type and layout, so the final capacity should be established through a site-specific design.
In simple terms: coordinate the roof services with the solar layout before construction. Keeping obstructions away from the most useful panel areas can protect future capacity without requiring expensive changes later.
For industrial sheds, the ridge direction matters
An industrial shed roof typically has two slopes, and the ridge direction affects how those surfaces can be used for solar.
An east-west ridge generally creates a south-facing slope and a north-facing slope. In central India, the south-facing slope can provide favourable annual solar exposure, although the best arrangement depends on the roof pitch, shading, wind loading and project economics.
A north-south ridge generally creates east- and west-facing slopes. These can still support solar panels, but generation will be distributed differently across the day. The annual yield difference compared with a south-facing arrangement depends on roof pitch, panel orientation, shading and system design; a fixed 10–15% penalty should not be assumed for every building.
North-light and saw-tooth roofs need a separate assessment. These roof forms are often designed to bring daylight into a factory, and the roof slopes may not be optimally oriented for solar generation. Reverse-tilt mounting can sometimes improve panel orientation, but it may increase structural loads, wind exposure, cost and spacing requirements.
If solar is part of the plan, discuss roof form and ridge direction with the architect before the structural design is finalised. Daylighting, ventilation, energy use, roof structure and solar generation should be considered together.
Key takeaway: ridge direction is much easier to coordinate at the design stage than after the shed is built. Ask the architect and solar designer to compare the likely generation and structural implications of the proposed roof options.
Structural provisioning: the cheapest insurance you will buy
A rooftop solar array adds permanent dead load and introduces wind-uplift forces that the building must safely resist. The design must consider the combined loads from modules, mounting structures, access arrangements and other rooftop equipment, along with the applicable wind and structural requirements.
For Indore and Bhopal, the structural engineer should determine the applicable basic wind speed and design parameters using the relevant standards and the specific site conditions. Refer to the IS 875 wind-loading reference as background material, but do not rely on an old or secondary document as the sole basis for the final design. The engineer should confirm the current applicable edition of IS 875 (Part 3), amendments and project-specific requirements.
Designing for solar at the outset may require changes to the RCC slab, beams, trusses or purlins. The cost depends on the span, building type, material quantities and structural design; it should not be assumed to be negligible in every project.
Retrofitting an under-designed building can be more complicated. It may require a structural assessment, strengthening work, scaffolding, additional steel, work at height and recertification. In some cases, the additional cost can undermine the project's economics.
Mounting anchors and waterproofing also need careful coordination. Cast-in inserts or other engineered attachment provisions can be considered during construction where the structural designer approves them. They must be located and detailed correctly. Drilling a completed roof is not automatically unsafe, but every penetration needs a suitable structural detail and a reliable waterproofing solution.
In simple terms: tell your structural engineer that rooftop solar is planned. Ask for a documented load assessment, applicable wind-load design and an approved mounting and waterproofing detail before construction is completed.
Electrical provisioning: three cheap things
A conduit. Consider a dedicated route from the roof to the planned inverter and electrical-panel location. A 40 mm conduit may be suitable for some projects, but the required diameter depends on the cable sizes, number of circuits, bend radius, derating and applicable electrical requirements. Decide the route and size with the electrical designer before plastering and finishing work begins. Retrofitting a concealed route can involve chasing finished walls or installing surface trunking.
Wall space. Identify a suitable location for the inverter and associated electrical equipment near the planned connection point, while respecting manufacturer clearances, ventilation, weather protection, access and electrical-safety requirements. A cramped or poorly ventilated location can make maintenance difficult and may affect equipment performance.
Earthing. Plan the earthing and bonding arrangement for the solar system as part of the electrical design. The required electrodes, conductors, protection devices and bonding method depend on the building's existing earthing system, equipment and applicable electrical standards. Coordinating trenches and earthing provisions during foundation work can avoid disruptive excavation later.
These provisions are not the solar system itself. They are the routes, equipment space and supporting electrical infrastructure that the future installation will need.
Key takeaway: coordinate the conduit route, inverter location and earthing plan before finishing work begins. The exact specifications should be set by the electrical designer rather than copied unchanged from another project.
The sanctioned load decision, which works in opposite directions
The right connection capacity depends on whether you are building a home or commercial premises, as well as the applicable tariff and metering rules. It should not be chosen solely to maximise future solar capacity.
The sanctioned load or contract demand, the approved connection type and the permitted solar capacity can all affect your options. If you expect to add solar later, confirm the applicable capacity limits and connection requirements with the distribution company before finalising the electricity application.
Increasing sanctioned load or contract demand later may involve application fees, additional charges, service upgrades, metering changes and processing time. The exact process depends on the connection and the discom's requirements.
For a home, it can be sensible to plan for future appliances and a possible rooftop solar installation. However, do not assume that applying for the largest possible sanctioned load is always free or that a three-phase connection is automatically required in every case above a single fixed threshold. Check the current supply code, tariff and discom requirements for the proposed connection.
For commercial and industrial premises, overestimating the required contract demand can be costly where the applicable tariff uses demand-based billing. The current MPERC tariff order sets out billing-demand rules and minimum billing provisions for relevant categories. The exact impact depends on the tariff category, voltage and connection terms.
So the planning approach differs:
- Home: assess expected appliance demand, future electrification, the intended solar capacity and the connection requirements together. Confirm whether a single-phase or three-phase supply is appropriate.
- Factory, shop or warehouse: estimate the facility's actual and planned demand, examine the applicable billing-demand rules, and discuss solar capacity and metering separately with the discom and solar designer.
A developer also needs to consider the distribution network serving the project. Transformer capacity and the ability to accommodate rooftop solar depend on the local network, existing connections and the applicable interconnection rules. A dedicated or larger transformer may be worth discussing at the layout-approval stage, but its required rating and any solar hosting limits must be confirmed with the utility rather than assumed from a universal percentage.
In simple terms: plan the connection around real and expected demand, then verify the solar capacity and network conditions with the discom before committing to the design.
Is solar actually required in Madhya Pradesh?
The requirements depend on the type of building, its size, use, location and the rules applicable to its approval. Do not assume that every private house must install solar, or that every large commercial building is automatically subject to the same requirement.
For larger commercial, institutional and other specified buildings, energy-conservation requirements may apply under the relevant building-code framework. The applicable threshold, compliance route, energy-performance requirements and certification process should be confirmed with the architect and the approving authority for the particular project.
The state's building rules should also be checked when designing rooftop structures, parapets and solar equipment. For example, the Madhya Pradesh Bhumi Vikas Rules contain provisions concerning building design and roof-edge protection. Do not assume that solar equipment is automatically excluded from every built-up-area or building-height calculation; the treatment depends on the relevant rule and approval conditions.
Key takeaway: confirm the applicable building, energy-conservation and approval requirements at the design stage. Your architect should identify which provisions apply to your building and what documentation is required before occupancy.
Should you just install it now?
Usually, the best approach is to separate the early planning work from the installation of the solar equipment.
Provision during the civil phase. Coordinate the roof layout, structural design, approved mounting details, cable routes, inverter location, earthing and connection requirements. These decisions are easier to incorporate while the drawings and construction programme are still being developed.
Install the hardware at the appropriate stage. Modules and inverters should be installed when the site is ready for safe installation and commissioning. A live construction site can expose equipment to cement dust, paint, welding debris and accidental damage. Commissioning also starts applicable warranty periods, so timing should be coordinated with the building handover and project schedule.
If you want to evaluate the complete installation, our rooftop solar price guide for Indore covers indicative system costs, while our subsidy guide explains the scheme-related questions to check. Typical home system sizes and economics are discussed in our 3kW guide and 5kW guide. Verify current prices, eligibility and subsidy conditions before making a decision.
In simple terms: make the building solar-ready during design and construction, then install and commission the solar equipment when the site and approvals are ready.
What to do while you still have the drawings
Five actions can make a future solar installation easier and reduce avoidable changes after construction.
Tell your architect to coordinate the rooftop services with the intended panel layout and shading study. Ask your structural engineer to assess the additional dead load, wind uplift and approved mounting details. Ask the electrical designer to plan a suitable conduit route, inverter location, cable sizing and earthing. Ensure that parapets and edge protection comply with the applicable building and safety requirements while accounting for potential shading. Finally, size the electricity connection according to expected demand, tariff implications and the solar arrangement you intend to use.
Send us your roof plan or elevation while it is still at the drawing stage. AutoSys can help review the proposed solar layout, identify likely shading and access constraints, and prepare an indicative system-capacity assessment for discussion with your architect and structural engineer. Final structural, electrical and regulatory decisions should be confirmed by the qualified professionals responsible for the project.
A complete solar EPC scope covers the agreed design, approvals, installation and commissioning. On a new building, however, the most useful solar-planning discussion often starts well before the panels are installed. If construction is already complete, a site assessment can establish the usable roof area, likely system capacity and any additional work required. Start with an assessment of rooftop solar installation for your property.
Frequently asked questions
How much does it cost to make a new building solar-ready?
The cost depends on the building and which provisions are required. Planning cable routes, equipment space, earthing and mounting details during design can reduce later rework. Retrofitting may involve surface trunking, wall repairs, excavation, waterproofing or structural modifications, so obtain a project-specific estimate rather than relying on a universal multiplier.
Where should the water tank and lift room go if I want solar?
Their location should be coordinated with the panel layout and a shading assessment. Placing taller obstructions towards the northern side of the roof can often help reduce shadows on panels to their south in central India, but the correct location depends on the building orientation, height and roof geometry. A centrally placed 3-metre structure can affect a substantial roof area, but the lost capacity must be calculated for the actual layout.
How high can my parapet be without shading the panels?
There is no single parapet height that is safe from shading for every roof. The effect depends on the parapet height, panel mounting height, setback, roof orientation and winter sun angles. Keep the shading impact in mind during design, but do not compromise the minimum parapet or edge-protection requirements that apply to the building.
What sanctioned load should I apply for on a new house?
Choose a connection capacity that accounts for expected appliance demand, future electrical loads and the proposed solar system. The sanctioned load and connection type can affect the available solar capacity and the approvals required. Confirm the applicable fixed charges, supply-phase requirements and metering rules with the discom before applying.
Should a factory also apply for extra sanctioned load?
Not automatically. Commercial and industrial connections may be subject to demand-based billing, including minimum billing-demand provisions. An unnecessarily high contract demand can increase fixed charges, depending on the tariff category and rules. Review the facility's expected and measured demand before deciding, and confirm the applicable provisions in the current tariff order.
Which way should an industrial shed ridge run?
An east-west ridge usually creates a south-facing roof slope that may be favourable for solar in central India. A north-south ridge creates east- and west-facing slopes, which can still produce useful generation. The best choice depends on the roof pitch, shading, structural design, factory daylighting requirements and the project's generation objectives.
Is solar mandatory on new buildings in Indore?
The answer depends on the building type, size, applicable energy-conservation provisions and local approval requirements. Do not assume that all residential buildings are exempt or that every large commercial building follows an identical rule. Ask your architect and the approving authority to confirm the requirements for the specific project.
Should I install the panels during construction?
Plan the structural, roof-layout and electrical provisions during construction, but install and commission the modules and inverters when the site is ready. This reduces the risk of construction-related damage and helps align commissioning and warranty periods with the project handover.
What should I tell my structural engineer?
Explain that rooftop solar is planned and provide the preliminary system capacity and mounting concept, if available. Ask the engineer to assess the additional dead load, wind uplift, load transfer to the building structure, roof waterproofing and the applicable current standards. The final design and any cast-in anchors or other mounting provisions should be specified and approved by the responsible structural engineer.